Construction Delays: When Architects Are Entitled to Additional Compensation
If a construction project is significantly delayed and the architect is not at fault, this ruling allows the architect to bill for the actual additional costs incurred—based on the personnel costs actually incurred, not the originally agreed-upon hourly rates. The Berlin Regional Court II awarded a planning consortium responsible for the major renovation of the Pergamon Museum an additional €332,565.63 in compensation. The decisive factor was that the delays were due to circumstances beyond the architects’ control.
Read more ►